Campus Progress

Campus Progress

Rose State College is adding student housing and a soccer program. A number of campus renovations will also be made with bond funds approved by voters last year. Check this page periodically for updates on these exciting new developments.

November, 2014 Bond Projects Updates 

  • Wellness Center Phase I (aquatics). The aquatics center (pool and associated areas) is complete. There remains some punch items to be completed (primarily the air supply louvers on the east gable end) but the CM firm is working to address those issues.
  • Wellness Center Phase II (Student Locker Room renovation). Demolition is complete. Plumbing should be complete next week, followed by electrical work and tile installation. Completion date is December, 2014.
  • Wellness Center Phase III (roof replacement). Roof replacement for the connection between aquatics and wellness center is substantially complete. Final work and inspection should occur around mid November.
  • Wellness Center Phase IV (storefront.) This project will replace the doors to the south entrance of the Wellness Center. This phase is under design and the expected bid date is February, 2015 with a completion date of May, 2015.
  • Social Sciences Building. Demolition work is complete and the restroom modifications are under way. This project will address restroom ADA compliance issues, new lighting, IT cabling, flooring, ceilings, finishes and entrance doorways. Electrical and plumbing upgrades are substantially complete. Projected completion date is tentatively scheduled for December 15, 2014.
  • Administration Building Design is 90% complete. This project will address restroom ADA compliance issues. Bidding and contract awards will occur in December with construction beginning in January, 2015. Anticipated completion is May, 2015.
  • Humanities Building Design is 90% complete. This project will address restroom ADA compliance issues, new lighting, IT cabling, flooring, ceilings, finishes and entrance doorways. Bidding and contract awards will occur in December, 2014, with construction beginning in January, 2015. Anticipated completion is May, 2015.
  • Fine Arts Building Design is 90% complete. This project will address restroom ADA compliance issues, new lighting and IT cabling throughout and new flooring, ceilings and finishes in the hallway areas. Bidding and contract award is scheduled for December with construction beginning in January, 2015. Anticipated completion is April, 2015.
  • Theater building. Design is 90% complete. This project will address lighting, flooring and finishes in the mezzanine area and new exterior doors. Bidding and contract award is scheduled for December, 2014, with construction beginning in January, 2015. Anticipated completion is April, 2015.
  • Engineering Technology Building. Design is 50% complete. This project will address restroom ADA compliance issues, new lighting, IT cabling, flooring, ceilings, finishes and entrance doorways. Bidding and contract awards will occur in April, 2015, with construction beginning in May, 2015. Anticipated completion is September, 2015.
  • Business Administration Building. Design is 50% complete. This project will address restroom ADA compliance issues, new lighting, IT cabling, flooring, ceilings, finishes and entrance doorways. Bidding and contract awards will occur in April, 2015, with construction beginning in May, 2015. Anticipated completion is September, 2015.
  • Science and Math Building. Design is 30% complete. This project will address restroom ADA compliance issues, new lighting, IT cabling, flooring, ceilings, finishes and entrance doorways. Bidding and contract awards will occur in November, 2015 with construction beginning in December, 2015. Anticipated completion is April, 2016.
  • Learning Resource Center conceptual design is complete. This project will provide for a complete renovation of the existing facility and expansion on the south and west sides of the building. The renovation includes new office space, new MEP, IT cabling, addition of a cafĂ© area and new reception area. The architect will begin development of design drawings within the next week to ten days. Bidding and contract award is tentatively scheduled for May, 2015 with construction commencing in June, 2015. Project completion is estimated to be in December, 2016.
  • IT Infrastructure Upgrade. VOIP phone upgrade is complete. New redundant fiber optic system will be installed and connected to the State One Net system. All buildings will receive IT cabling upgrades. Wireless system will be upgraded. A backup generator for the data center will be installed. Design is approximately 90% complete and bidding for the initial phases of fiber optic installation and IT cabling upgrades are scheduled for November, 2014 with contract awards in December. Construction will begin in January with an estimated completion date of June, 2015. 
  • HES building. MEP Upgrade Conceptual design in underway. Anticipated bidding and construction to begin in November, 2015, with completion in the summer of 2016.
  • Student Center Lounge. Upgrade conceptual design is underway. Anticipated bidding date is February, 2015 with a completion date of June, 2015.
  • 15th Street Sign Upgrade. Initial Design concepts to be developed in the Spring of 2015. No bidding or construction dates have been scheduled at this time.

 

Rose State College
6420 S.E. 15th Street.
Midwest City, OK 73110-2704
Phone: 405-733-ROSE (7673)
Toll Free: 866 621-0987

© Copyright 2014 Rose State College
All Rights Reserved
Designed by Element Fusion
Powered by Radium3